2018 Pugh Street Waterline Replacement (completed)

Pugh Street Waterline Replacement

  1. Waterline replacement will start at Easterly Parkway and proceed to Beaver Avenue
  2. SCBWA will be replacing approximately 4,500 ft of 4" and 6" cast iron pipe with 12" ductile iron waterline. 
  3. Anticipated completed timeframe is the middle of September. 
***Traffic patterns will be altered with potential limited closures, we encourage you to seek an alternate route
  • Curb work and restoration should be completed by the end of September.

Please check CATA's website for updated bus route detours and delays.