2018 Water Main Replacements

  • South Outer and West Outer Drive -----COMPLETED
    • Replacing 4" cast iron pipe with 4" ductile iron pipe
    • Will be done in conjunction with College township street projects
  • Easterly Parkway---COMPLETED
    • Intersection of William and Garner Streets
    • Replacing 12" cast iron pipe with 12" ductile iron pipe
    • Replace approximately 375 feet
    • Will be done in conjunction with the Borough 
  • Tank 6--In Progress and will continue in 2019
    • Main water line- removing restrictions where it converts from 16" to 8"
  • Cricklewood Drive--2nd PHASE DONE
    • Project started in 2017 going from Toftrees Ave to to Wilts Lane
    • In 2018 we are continuing from Wilts Lane and end close to 940 Cricklewood Drive
    • Replacing 8" cast iron pipe with 12" ductile iron pipe