2022- Final Phase of Boalsburg Pike Waterline Replacement

2022 Waterline Replacement season will complete the third and final stage of Boalsburg Pike.  The final stage is from Lee Ave to Boal Ave.  Once there is nice weather, crews will start work.  Just as the last phase, there will be delays in travel at times.  Please use caution when driving through the work area.  

Boalsburg Pike Waterline Replacement

  • The project was started in 2019 with the installation of HDPE pipe under Spring Creek
  • 2,800’- total length of 8” ductile iron pipe to replace the 8” cast iron pipe (this will be done in two sections)
    • Lee Avenue to Apollo Drive- The crews have installed 1,200' and at the intersection of Belle Ave, they have 200' to finish this section.  
    • Lee Avenue to Boal Avenue
  • SCBWA crews will be installing the water line
  • Flaggers will be in place to assist with traffic
    • Traffic patterns will be altered with potential limited closures, we encourage you to seek an alternate route
  • Work hours will be between 7am and 4:30 pm

Affected Area: 

Google Map

Status Update (chronological): 

The last phase of this project will be completed in 2022.