Boalsburg Pike Waterline Replacement

boalsburg pike installing pipe

Boalsburg Pike Waterline Replacement

  • The project was started in 2019 with the installation of HDPE pipe under Spring Creek
  • 2,800’- total length of 8” ductile iron pipe to replace the 8” cast iron pipe (this will be done in two sections)
    • Lee Avenue to Apollo Drive- The crews have installed 1,200' and at the intersection of Belle Ave, they have 200' to finish this section.  
    • Lee Avenue to Boal Avenue
  • SCBWA crews will be installing the water line
  • Flaggers will be in place to assist with traffic
    • Traffic patterns will be altered with potential limited closures, we encourage you to seek an alternate route
  • Work hours will be between 7am and 4:30 pm

Affected Area: 

Google Map

Status Update (chronological): 

Restoration is underway.