Pugh Street Waterline Replacement

Pugh Street Waterline Replacement

  1. Waterline replacement will start at Easterly Parkway and proceed to Beaver Avenue
  2. SCBWA will be replacing approximately 4,500 ft of 4" and 6" cast iron pipe with 12" ductile iron waterline. 
  3. Anticipated completed timeframe is the middle of September. 
***Traffic patterns will be altered with potential limited closures, we encourage you to seek an alternate route
Week of May 7th
  • Traffic Control Set Up
  • Mobilization
Week of May 14th
  • Saw Cutting
  • Tap at Easterly Parkway

Please check CATA's website for updated bus route detours and delays.  

Status Update: 

Construction site prep work is under way.

For questions or to report problems: 814-238-6766